SERVICE (cont.)
Location:
The solenoid valve is located inside the lower right
front of the brewer.
Test Procedure:
1. Disconnect the brewer from the power source and
draw 1/4 gallon of water from faucet.
2. Remove both wires from the solenoid valve coil
terminals.
3. With a voltmeter check the voltage across the
white/blue wire and white wire. Connect the brewer
to the power source. The indication must be 120
volts ac for 120/208V and 120/240V three wire
models.
4. Disconnect the brewer from the power source.
If voltage is present as described, proceed to #5.
If voltage is not present as described, refer to the
wiring diagrams and check brewer wiring harness.
5. Check for continuity across the solenoid valve coil
terminals.
If continuity is present as described, reconnect the
white and white/blue wires.
If continuity is not present as described, replace the
solenoid valve.
P2232
FIG. 29 REFILL SOLENOID VALVE
6. Check the solenoid valve for coil action. Connect
the brewer to the power source. Listen carefully in
the vicinity of the solenoid valve for a "clicking"
sound after approximately 1 second, as the coil
magnet attracts.
7. Disconnect the brewer from the power source.
If the sound is heard as described and water will not
pass through the solenoid valve, there may be a
blockage in the water line before or after the solenoid
valve or, the solenoid valve may require inspection for
wear, and removal of waterborne particles.
If the sound is not heard as described, replace the
solenoid valve.
Removal and Replacement:
1. Remove all wires from the solenoid valve coil.
2. Turn off the water supply to the brewer.
3. Disconnect the water lines to and from the sole-
noid valve.
4. Remove the two #8-32 slotted head screws hold-
ing the solenoid valve and mounting bracket to the
brewer trunk.
5. Lift-out the solenoid valve.
6. Remove the two #10-32 slotted head screws hold-
ing the solenoid valve to the mounting bracket.
7. Securely install the new solenoid valve to its mount-
ing bracket.
8. Attach the solenoid valve and mounting bracket to
the brewer trunk.
9. Securely fasten the water lines to and from the
solenoid valve.
10. Refer to Fig. 30 when reconnecting the wires.
REFILL SOLENOID VALVE
WHI/BLU to DBC Control Board J1-12
WHI to DBC Control Board J1-3
P799
FIG. 30 SOLENOID VALVE TERMINALS
32248 100500